Intersection of University Drive and 32nd Avenue South in Fargo to close on Wednesday

FARGO, N.D. (KVRR) — A busy intersection will close this upcoming week in Fargo. University Drive at 32nd Avenue South will close on Wednesday as construction continues on Phase 2 of Segment 3 of the reconstruction project. The short-term closure is expected to last about three weeks. It will allow crews to safely complete essential underground utility work. The closure…

Final phase of 32nd Avenue construction underway

Construction Barrel located at the intersection of 32nd Avenue and University Drive South. 4/28/26.FARGO — Work is well underway on the final phase of road construction on 32nd Avenue South in Fargo. This year, the construction is focused east of University Drive, with work also being done on 15th Street South and stretching to the Red River. Construction crews will…

Primary contractor on 32nd Ave. to receive $150,000 incentive for completing project early

FARGO (KFGO) – Work on the 32nd Avenue project in south Fargo is close to wrapping up. City Design and Construction Division Engineer Jason Leonard said the road will likely open Saturday. Work on the $18 million project began in mid-April. Leonard said the major construction was between 15th and 23rd Streets. “Storm sewer-trunk main that will eventually to the…

Significant progress reported on 32nd Ave. S project in Fargo

FARGO (KVRR/KFGO) – Phase 1 of the 32nd Avenue South improvement project, which included full reconstruction of the section between west of 15th Street South and east of 17th Street, is officially complete. While it marks a major milestone in the reconstruction of one of Fargo’s key corridors, the outside lanes between west of 15th Street and east of 17th…

Crews working hard to complete construction on 32nd Avenue South in Fargo

FARGO, N.D. (KVRR) — The City of Fargo is currently on track with the second phase of its reconstruction of 32nd Avenue South. The public was invited to share their concerns and ask questions about the ongoing project. Currently, the project this year is focused on the streets between 22nd Street South and 15th Street South. Several businesses are on…

Open House Discussion Regarding 32nd Avenue Reconstruction

Project officials plan to have the forum every other week, on Tuesdays, from 10:30-11:00 A.M.

FARGO, N.D. – The 32nd Avenue reconstruction efforts are moving forward, and project organizers want to make sure the community’s voices are heard. To that end, they’re holding informational, open-house style meetings at the John Carlson branch of the Fargo Public Library. Today, May 6, was the first one. City officials and contractors were on hand to answer any questions…

Motorcycle Crash Leaves Man Seriously Injured

The North Dakota Highway Patrol says the man was badly hurt despite wearing a helmet.

FARGO, N.D. – The North Dakota Highway Patrol is providing information regarding a motorcycle crash that occurred in the afternoon of Friday, April 25. At 2:42 P.M., a 67-year-old man was driving his 2014 Harley-Davidson westbound on 32nd Avenue South in Fargo. He apparently took the curve improperly, causing him to crash in the west gravel ditch. The driver sustained…

25th Street opens at 32nd Avenue S.

FARGO, N.D. (KVRR/KFGO) – Another phase of the 32nd Avenue reconstruction project in Fargo is complete. The north and southbound lanes of 25th Street through the 32nd Avenue S. intersection opened Saturday morning with a new signal system to control the intersection. Work on the first of the two-segment project continues west of 25th Street. Segment 1 will be completed…

UPDATE: Fargo Police locate vehicle connected to Thursday shooting

JULY 8 UPDATE — FARGO, N.D. (KVRR/KFGO) — Fargo Police say they found the SUV they were looking for in connection with a Thursday night shooting. The department says they located gray 2010 GMC Terrain with North Dakota license plates 2BLESS, based on tips from the community. Police responded after reports that shots were exchanged outside Park Place Apartments near…

Fargo’s 32nd Avenue South Rebuild Begins

FARGO, N.D. (KVRR) — The 32nd Avenue Reconstruction project involves rebuilding 1.5 miles in multiple segments from 32nd Street South through University Drive over the coming years. Reconstruction on Segment 1 between 32nd Street and 22nd Street will begin in spring 2023 and last through fall 2023 leaving segment 2 reconstruction from 22nd Street through University Drive slated to begin…