FM DIVERSION

Judge Allows Non-Waterway Work To Resume On FM Diversion Project

The project has been challenged by upstream residents who argue the project will lead to more flooding on their land

MINNEAPOLIS, MN — A federal judge has cleared the way for some work to resume on a massive flood control project in the Fargo-Moorhead area. District Judge John Tunheim on Monday ruled work could resume on certain portions of a $2.2 billion diversion aimed at steering the Red River safely past the cities in times of flooding. Fargo and Moorhead have…

FM Diversion Gets $750 Million in Federal Funding, Injunction Lift Pending

The next step is for a Minnesota judge to lift a temporary injunction that was put on the project

FARGO, N.D. — State and local leaders sign a partnership securing 750 million dollars for the F–M Diversion. The goal of the agreement is to get the project done in six to eight years. “It’s not if we’re going to flood. We are going to flood. Let’s get that permanent protection in place to protect lives and property and over time…

Watershed Group To Hold Public Hearing on Diversion Project

During a packed meeting in Barnesville, the board voted unanimously to hold the hearing at a date and location that have yet to be determined.

BARNESVILLE, MN (KFGO) – The Buffalo-Red River Watershed Board has voted to take the unusual step of holding a public hearing on whether it will issue a permit for the FM Diversion. During a packed meeting in Barnesville, the board voted unanimously to hold the hearing at a date and location that have yet to be determined. With more than…

Army Corps 2019 Work Plan Includes Another $35 Million For Fargo-Moorhead Flood Protection

The funding will cover work on the inlet structure south of Horace, the control structure on the Wild Rice River as well as additional design work

FARGO, ND — More federal money is going into flood protection for Fargo-Moorhead. Senators Hoeven and Heitkamp announced that $35 million is included for flood protection construction in the Army Corps 2019 work plan. Hoeven says the “funding comes at a critical time and will help ensure the project’s procurement process and construction can move forward”. The funding will cover work…

Federal Judge Approves Bypass Construction Near Horace

The bypass work will start next week and will be done as soon as possible

  HORACE, ND — Good news for those dealing with a long detour southwest of Fargo for the past couple of months. A federal judge has approved an agreement between those involved in the FM Diversion Project lawsuit that will allow construction of a bypass to reconnect traffic on Cass County 17 south of Horace. The road was torn-up for…

Governors Burgum and Dayton Agree to Meet on F-M Diversion Project

The two governors talked over the phone to quote "to try to find a path forward'' for the $2.2 billion project

  REGIONAL — Governors Doug Burgum and Mark Dayton have agreed to discuss ways to restart the F-M flood diversion project. The two governors talked over the phone to quote “to try to find a path forward” for the $2.2 billion project. The 30-mile channel has been approved by Congress and work had begun but a federal judge from Minnesota…

Judge in St. Paul Hears F-M Diversion Arguments

Two Groups Wants Ongoing Contruction Halted

ST. PAUL, Minn. — A judge in St. Paul has heard arguments on the dispute over the F-M Diversion. U.S. District Court Judge John Tunheim heard arguments regarding motions made by the U.S. Army Corps of Engineers, the Minnesota DNR and the Richland/Wilkin Joint Powers Association. The JPA and DNR are trying to halt ongoing construction of the diversion while…

Minnesota Judge To Hear Diversion Arguments Tuesday

Could Decide To Halt Construction of F-M Diversion

Both sides in the legal battle over the Red River diversion could get some clarity soon. A federal judge in Minnesota will hear arguments Tuesday on whether construction of the project should be halted until developers receive the necessary permits from the Minnesota DNR. The 36-mile channel is envisioned as the solution to the frequent flooding threat to Fargo-Moorhead. But…

Fargo City Engineer Resigns

Walker, in an email to engineering employees, says she's looking for more balance in her life

FARGO, ND — Fargo City Engineer April Walker has resigned. Walker has been with the engineering department for 15 years and was heavily involved in the F-M Diversion in recent years. Walker, in an email to engineering employees, says she’s looking for more balance in her life. She says she was not asked to resign and isn’t leaving for another…

Local Farmer Calls Authorities on FM Diversion Worker

He says he has a court order preventing any diversion-related work on his land

  CASS COUNTY, ND — The Cass County Sheriff’s Office was called this morning about F-M Diversion workers. Richard Cossette says the contractor came onto his property south of Horace. He says he has a court order preventing any diversion-related work on his land. Cossette says the contractor left voluntarily. He has maintained that his appraisal is far below what was…